A revised agency rollout schedule
approved September 15 by the SCEIS Executive Oversight Committee
adjusts the timing of future implementations, while keeping the original Project completion date of July 2010. In the
new schedule, agencies will go live in
just two large rollouts, rather than a series of frequent smaller
rollouts. (The upcoming FF2 rollout on November 3, 2008, is
unchanged.) In the revised plan, the previously-identified
Functional Fit 3 and 4 agencies and most of the broader-scope
Wave agencies will all go
live together, in a large Phase 3 rollout on November 2, 2009.
A final rollout, Phase 4, will complete the SCEIS
agency implementations on May 3, 2010.
Between now and
Phase 3, the SCEIS Project Team is working on development of the Human
Resources / Payroll modules and a number of
projects with enterprise-wide impacts,
to establish the foundation set for all additional rollouts.
What are the Phase 3 and Phase 4 rollouts?
Phase 3 (November 2, 2009) combines
into one big rollout the approximately 20 remaining agencies
identified as "functional fits" for the SCEIS system's existing
functionality; plus about 15 broader-scope agencies for which SCEIS
will need to add functionality. Phase 4 (May 3, 2010), is made
up of
four other broader-scope agencies.
For all agencies,
Human Resources functionality will be added after their initial
go-live dates.
The new schedule recognizes both the interdependence of
the Foundation Set projects,
and the necessity to manage agencies' implementation preparations as efficiently
as possible. Is this a "Big Bang?"
The Phase 3 rollout in 2009 has
been called a "big bang," but that's not really accurate. In the language of an enterprise resource planning (ERP) project, the phrase
"big bang" refers to rolling out all end-users and all
modules of the
system at once on Day One. Instead, SCEIS is using a
phased-implementation approach.
-
SCEIS launched with just the Finance and Materials
Management modules, rolling out to just a few
agencies.
-
Two additional rollouts
add more agencies.
-
In October 2009, Human Resources
functionalities will be added for agencies which are already
live.
-
In November 2009,
Phase 3 will add a large
group of agencies and the additional functionality to support
them.
-
In May 2010, Phase
4 will roll out the last four agencies, to
complete the agency implementations.
-
Human Resources
functionalities will be added to newly-implemented agencies
after their initial Finance and Materials Management go-lives.
|